(1) Project plans submitted in accordance with these rules will be considered inactive and closed if:
- (a) Finalized construction drawings and specifications are not submitted for review and approval within 365 calendar days of the project’s schematic plans submission date;
- (b) A plan of correction is not submitted for review and approval within 90 calendar days of the construction document review date;
- (c) A Project Substantial Completion Notice is not received within 550 calendar days of the Notice of Construction Document approval date;
- (d) A Project Substantial Completion Notice is not submitted for a phased construction project within 550 calendar days of the last completed phased inspection date; or
- (e) A plan of correction is not submitted for review and approval within 90 calendar days of receipt of the Project Inspection Report for the project.
- (2) The Oregon Health Authority will notify the project sponsor 15 business days prior to closing any project and may grant one or more extensions for additional periods of time not exceeding 90 calendar days each, based on relevant information provided by the project sponsor.
- (3) A project sponsor may request to reopen a project after it has been closed. The project sponsor must submit a new fee in accordance with OAR 333-675-0230, Table 1 and verify the accuracy of all previously submitted materials before review resumes. The project will be subject to any new rules in effect at the time that the new fee is received.
Statutory/Other Authority
ORS 410.070, 441.025, 441.060, 443.450, 443.860 & 443.886
Statutes/Other Implemented
ORS 410.070, 441.060, 443.450, 443.860 & 443.886
History
PH 7-2025, adopt filed 03/01/2025, effective 03/01/2025