(1) The department will review all preliminary certification applications, other than those participating in the small premium project process, to determine whether:
- (a) All sections of the application are complete as outlined in the Opportunity Announcement.
- (b) The applicant has submitted the required fee.
- (c) The project meets the definition of an energy conservation project.
(d) The applicant is applying prior to the installation or construction of the project.
- (A) If the applicant applies after installation or construction of the project has started, the department will deny the application unless a written explanation of the special circumstances is received and approved by the director.
- (B) Failing to submit a timely application or the fact that the project was not selected for a grant or tax credit under this or prior department programs does not constitute special circumstances.
- (e) The energy conservation project is located in Oregon.
- (2) If the department finds that the application is complete, the application will move into the competitive review process and the department will notify the applicant in writing.
- (3) The department may deny incomplete applications and notify applicants in writing of the reason for denial of the application.
- (4) The department considers the completeness review a test; the decision to deny an incomplete application is not subject to review under ORS chapter 183.
Statutory/Other Authority
ORS 469.040 & 469B.306
Statutes/Other Implemented
ORS 469B.270 - 469B.306 & 315.331
History
DOE 4-2016, f. & cert. ef. 11-14-16
DOE 6-2012, f. & cert. ef. 6-19-12
DOE 12-2011(Temp), f. & cert. ef. 12-23-11 thru 6-19-12