(1) Role of the agency.
- (a) The agency must notify the department of Class 2 projects.
- (b) The agency shall determine that the design incorporates all reasonable cost-effective ECMs. ECMs or ECM packages with a Simple Payback shorter than equipment life shall be considered cost-effective for Class 2 Buildings. The agency, with assistance from the design team as necessary, shall provide preliminary benefit/cost results for each ECM implemented.
- (c) The agency must send the list of energy efficiency measures included in the building design to the department.
- (d) Upon completion of construction, the agency must send a list of the measures that were actually installed in the building to the department.
- (2) Role of the department. The department shall be available to the agency to advise or suggest potential energy saving measures.
Statutory/Other Authority
ORS 276.900 - 276.915
Statutes/Other Implemented
ORS 469
History
DOE 6-2017, f. & cert. ef. 8-15-17
DOE 5-2011, f. & cert. ef. 6-27-11
DOE 5-2008, f. 7-29-08, cert. ef. 8-1-08
DOE 1-2003, f. & cert. ef. 1-10-03
DOE 4-2001, f. 11-5-01, cert. ef. 11-15-01
DOE 1-1998, f. & cert. ef. 3-26-98
DOE 1-1990, f. & cert. ef. 4-2-90