The agency is authorized to enter into such contractual and other arrangements as may be necessary or convenient to design, develop, operate and finance a project at state-owned or state-rented facilities. Utilities may be vendors. The procedure shall be:
- (1) Upon entering into a commitment with a vendor, the agency appoints representative(s) to work with the vendor to develop the project. Within three months the agency representative(s) and the vendor complete a project plan, including commissioning and training; develop a detailed budget; decide the allocation of risks and responsibilities of each party from project development through operation; determine costs to be assumed by the agency and by the vendor; determine length of agreement; set timelines.
- (2) The agency and the vendor execute a written agreement within two months of completing the above tasks.
- (3) The Department resolves disputes between agency and vendor arising from the project. The director’s decision is final.
- (4) If changes to the project are made subsequent to the written agreement, the agreement may be amended.
Statutory/Other Authority
ORS 469.752 - 469.756
Statutes/Other Implemented
ORS 469.752 - 469.756
History
DOE 2-1994, f. & cert. ef. 12-12-94
DOE 1-1992, f. & cert. ef. 4-30-92