In addition to application requirements pursuant to 141-093-0105, the applicant must provide the following information in an application:
- (1) A JART recommendation for processing the proposed project under this General Permit.
- (2) Map clearly illustrating location of the proposed ocean renewable energy facility placement relative to a REFSSA, REPA or RUMA.
- (3) A completed Resource Inventory and Effects Evaluation pursuant to Part Five of the Territorial Sea Plan. For proposed projects within a RUMA, the Resource Inventory and Effects Evaluation must clearly demonstrate no significant adverse effects on inventoried marine resources and uses. Pursuant to the Territorial Sea Plan, Part Five D., a Resource Inventory and Effects Evaluation is not required for proposed projects located at the NW National Marine Renewable Energy Center- Mobile Ocean Test Berth.
- (4) Description of how project meets the definition of “demonstration project” or “research project” as defined in this Rule.
(5) Project description including:
- (a) Description and quantity of all project components including anchoring system and other fixed components, tethering and floating components.
- (b) Area of ocean floor to be covered by anchors and any other equipment to be affixed to the ocean floor.
- (c) Methods and timing for facility deployment and recovery.
- (d) Identification of any project components expected to be decommissioned in-place.
- (e) Scaled plan view and cross-section drawings including the maximum ocean surface area that the facility will occupy considering drift area of floating components.
- (f) Facility inspection and contingency plan describing nature and timing of inspections and contingency plans for events including but not limited to: sinking or disconnection of floating components, substantive movement of anchors from the point of placement, entanglement of fishing gear, any release of fluids or any exposure of any buried components.
- (6) If project includes cables, pipes or conduit from device(s) to the ocean shore, application must describe method for placement consistent with Part Four of the Territorial Sea Plan. On-shore terminus of pipes, cables other conduit must be clearly identified. Any on-shore project components must be authorized by a state Ocean Shore Permit as administered by Oregon Parks and Recreation Department.
Statutory/Other Authority
ORS Chapter 183, ORS 196.810, ORS 196.817, ORS 196.485(3), ORS 197.180 & ORS 196.405-583
Statutes/Other Implemented
ORS 196.600-692 & ORS 196.795-990
History
DSL 55-2018, minor correction filed 01/05/2018, effective 01/05/2018