- (1) General Conditions Apply. All the conditions set forth in OAR 141-093-0135 apply to this GP.
- (2) Temporary Impacts Only. No conversion of wetland to upland is allowed. All material placed in wetlands must be spread in a thin layer before the onset of winter rains.
- (3) Removal of Woody Vegetation. Removal of woody vegetation must be limited to the minimum amount needed to complete the activity, including removal site access.
- (4) Maintenance of Riparian Buffer. Where practicable and necessary to complete the activity, removal of woody vegetation is limited to the north or east sides of the stream channel.
- (5) No Operation of Equipment in the Water Allowed. Equipment used to remove material must operate from top of bank position when feasible, otherwise from a dry position below top of bank.
- (6) Design to Limit Maintenance. To the extent practicable, the project must be implemented to naturally maintain inlet and outlet connections with the main stream channel.
- (7) Erosion Control. As necessary, erosion control measures must be installed and maintained during the activity and after disposal, so as to prevent discharge into waters of this state.
Statutory/Other Authority
ORS 196.600 - 196.692 & 196.795 - 196.990
Statutes/Other Implemented
ORS 196.600 - 196.692 & 196.795 - 196.990
History
DSL 67-2018, minor correction filed 01/05/2018, effective 01/05/2018
DSL 3-2012, f. 9-28-12, cert. ef. 9-29-12
DSL 2-2012(Temp), f. & cert. ef. 4-2-12 thru 9-28-12