The Division shall review the following applications to determine if the proposed hydroelectric project is to be constructed on lands within the jurisdiction of the Board:
- (1) Applications with the Federal Energy Regulatory Commission (FERC) for a preliminary permit or license to operate a hydroelectric project or for an exemption from the FERC licensing process.
- (2) Applications for a right to appropriate water for hydroelectric power under ORS Chapter 537.
- (3) Applications for a preliminary permit or a hydroelectric license under ORS Chapter 543.
- (4) Applications for local land use approval for a proposed hydroelectric project.
- (5) Applications for a site certificate from the Energy Facility Siting Council (EFSC) under ORS Chapter 469.
Statutory/Other Authority
ORS 273 & 274
Statutes/Other Implemented
ORS 273 & 274
History
LB 2-1986, f. & ef. 2-19-86