- (1) Bids. Except as permitted by ORS 279C.340 and OAR 137-049-0430 when all bids exceed the cost estimate, a Contracting Agency shall not negotiate with any Bidder prior to Contract Award. After Award of the Contract, the Contracting Agency and Contractor may modify the resulting Contract only by change order or amendment to the Contract in accordance with 137-049-0910.
- (2) Requests for Proposals. A Contracting Agency may conduct discussions or negotiations with Proposers only in accordance with the requirements of OAR 137-049-0650.
Statutory/Other Authority
ORS 279A.065
Statutes/Other Implemented
ORS 279C.340 & 279C.375
History
DOJ 20-2005, f. 12-27-05, cert. ef. 1-1-06
DOJ 11-2004, f. 9-1-04, cert. ef. 3-1-05