The Department will determine tide gate planning project application eligibility using criteria including but not limited to the following:
- (1) The application must demonstrate that the study scope will include all elements needed to develop a shovel ready tide gate project consistent with OAR 123-046-0060(1).
- (2) All required permits and regulatory authorizations must be addressed through the study scope.
- (3) The study scope must result in feasibility documentation consistent with OAR 123-046-0060(2).
- (4) The study scope must include a plan to communicate with all impacted landowners throughout the course of the planning project.
Statutory/Other Authority
ORS 285A.075 & Ch 10, OL 2020
Statutes/Other Implemented
Ch 10, OL 2020
History
OBDD 4-2021, adopt filed 03/15/2021, effective 03/15/2021