(1) To approve an application for assistance from the fund, the Authority must make the determinations as follows:
- (a) The project is consistent with the requirements governing assistance from the fund. If the Authority determines that the applicant and/or the proposed project do not meet the requirements of this section, the Authority may reject an application or require further documentation from the applicant;
- (b) The requisite need for the project has been demonstrated in the application or the local planning process;
- (c) The port has certified to the Authority that there will be adequate funds available to repay any loans made;
- (d) The loan security includes the pledge of revenues and/or other funds are sufficient, when considered with other security, to assure repayment;
- (e) The applicant is willing and able to enter into a contract with the Authority for repayment of the loan;
- (f) The project is ready to proceed including all necessary permits required by federal, state and local agencies;
- (g) The project activities constitute an eligible project;
- (h) Moneys in the fund are or will be available for the project;
- (i) The requirements under ORS 285A.055 for approval have been satisfied;
- (2) The Authority may provide preliminary approval of a loan application at any time and identify all necessary requirements for final approval.
- (3) If the application is denied, the matter will be set aside unless the applicant requests further action under ORS Chapter 183.
Statutory/Other Authority
ORS 285A.075
Statutes/Other Implemented
ORS 285A.669 - 285A.732
History
OBDD 12-2024, amend filed 05/31/2024, effective 05/31/2024
EDD 20-2009, f. 10-30-09, cert. ef. 11-1-09
EDD 6-2006, f. 10-30-06, cert. ef. 10-31-06
EDD 16-2004, f. & cert. ef. 8-2-04
EDD 1-2004(Temp), f. & cert. ef. 2-3-04 thru 8-1-04
EDD 8-2002, f. & cert. ef. 5-1-02