Okla. Admin. Code § 785:50-9-42
After completion of construction, acceptance by the applicant, and receipt of satisfactory test results that all work has been performed according to specifications (if such tests are required), the final release of retainage may be made with approval of the project by the Board.
Added at 10 Ok Reg 3333, eff 7-1-93
Amended at 23 Ok Reg 3086, eff 7-27-06
Amended at 31 Ok Reg 2512, eff 9-12-14
Amended at 35 Ok Reg 2243, eff 9-14-18