The purpose of the planning document is to present the findings of the engineer or other qualified professional as approved by the Board in a precise fashion with enough attention given to detail so as to allow adequate review of the project by the owner and applicable regulatory agencies. A planning document must be submitted to the Board. The document shall contain but not be limited to the following information:
- (1) Identification of the planning area boundaries and characteristics, the existing problems and needs related to wastewater management, and the projected needs and problems through the design life of the project.
- (2) Cost and effectiveness analysis certification of meeting State and federal water quality and public health requirements.
- (3) All basic information necessary for the design of the sewage system and/or treatment works.
- (4) Adequate evaluation of the environmental impacts of alternatives in accordance with Part 7 of this subchapter (relating to Environmental Review and Determination) to support the cost effectiveness analysis together with a resolution passed by the applicant which accepts the planning documents and provides a commitment to build the proposed project.
- (5) A demonstration that the project is consistent with the State's approved Water Quality Management Plan established by Section 208 of the Clean Water Act.
- (6) The applicant shall submit a statement of the project engineer's most current estimate of project cost itemized as to major facilities or items including land and right-of-way costs, fees of engineers, brownfield assessment fees, all legal fees, fees of registered financial advisors and/or consultants, contingencies and interest during construction.
Added at 10 Ok Reg 3333, eff 7-1-93
Amended at 15 Ok Reg 2881, eff 7-1-98
Amended at 17 Ok Reg 2772, eff 7-1-00
Amended at 28 Ok Reg 1026, eff 7-1-11
Amended at 31 Ok Reg 2512, eff 9-12-14
Amended at 33 Ok Reg 1954, eff 9-11-16
Amended at 35 Ok Reg 2243, eff 9-14-18