Okla. Admin. Code § 785:1-9-1
Any permit, license and certification for an activity regulated by the Board, as described in 785:1-9-2, shall be issued or denied within six (6) months after the Board receives a completed application or notice of completion therefor which is deemed complete by the Board, unless the time is extended as provided in 785:1-9-3. If the application for a permit, license, or certification requires notice and opportunity for hearing, the Board shall issue or deny the application within six (6) months of the end of the notice period.
Added at 10 Ok Reg 3267, eff 6-25-93
Amended at 40 Ok Reg 1300, eff 8-11-23