(a) A construction conference may be called periodically by, when applicable, the CFMO or his designee or the Design Consultant to discuss:
- (1) Project progress as it relates to schedule.
- (2) Payment requests and their status.
- (3) Change order requests and their status.
- (4) Special problems and remedial action required.
- (5) Results of previous remedial action.
- (6) Other subjects as required.
- (b) The meeting shall be chaired by the CFMO or his designee or the Design Consultant. Minutes of the meeting shall be kept by a designee of the CFMO, typed, and distributed to all applicable parties within five (5) working days.
Added at 36 Ok Reg 1970, eff 9-18-19
Amended at 40 Ok Reg 1664, eff 9-1-23