- (a) The Department shall establish and maintain meaningful project schedules, establish accountability for project components, manage the construction program and measure performance. Since it is not possible to create a single project development process or schedule that will prove effective for every project every time, the Department shall establish a milestone based project schedule for each project identified in the Eight Year Construction Work Plan.
- (b) As more detailed information becomes available during the course of project development, the Department shall facilitate necessary modifications to the scope, schedule and/or budgets of approved Eight Year Construction Work Plan projects through a formal revision process.
Amended at 17 Ok Reg 1368, eff 5-11-00
Amended at 29 Ok Reg 1488, eff 6-25-12