Okla. Admin. Code § 460:20-27-11
(b) Baseline information. The application shall include the following baseline hydrologic information, and any additional information required by the Department.
(c) Baseline cumulative impact area information.
(f) Probable hydrologic consequences determination.
(3) The PHC determination shall include findings on:
(D) What impact the proposed operation will have on:
(g) Cumulative hydrologic impact assessment.
(i) Ground-water monitoring plan.
(j) Surface-water monitoring plan.
(2) The plan shall identify the surface-water quantity and quality parameters to be monitored, sampling frequency, and site locations. It shall describe how the data may be used to determine the impacts of the operation upon the hydrologic balance.