(a) A certified organization is required to submit an election plan for approval. The election plan must include:
- (1) a list of newspapers where notices shall be published and dates of publication;
- (2) a notice to county agents indicating referendum date or other canvassing dates;
- (3) a draft ballot;
- (4) a draft press release;
- (5) a draft board member petition;
- (6) information on whether the election will be conducted by mail or physical ballot; and
- (7) the date of the referendum. The date of the referendum must be within ninety (90) days following certification.
- (b) If the election plan is denied, the Commissioner or his designee shall provide a written explanation of the denial within ten (10) working days of receipt of the plan. The certified organization may then re-submit the plan.
Added at 17 Ok Reg 299, eff 11-2-99 (emergency)
Added at 17 Ok Reg 2871, eff 7-13-00