- (a) Primary settling. All sewage entering a lagoon must first pass through a septic tank for primary settling.
- (b) Total retention. All lagoons shall be total retention.
- (c) Location. Installers shall not locate lagoons where vegetation, timber, or terrain could interfere with prevailing wind action or shade the lagoon during daylight hours.
- (d) Prohibitions. The owner/operator shall not dispose or store wastes or contaminants other than sewage in the lagoon. The owner/operator shall not discharge or dispose of sludge from the lagoon prior to obtaining approval from the DEQ.
(e) Closure. A closure plan shall be submitted for all lagoons being classified as small public on-site sewage treatment systems or when DEQ requires closure of a lagoon when a public health or safety issue arises and will include:
- (1) A description of how the wastewater will be disposed.
- (2) A description of how the sludge will be disposed if more than six (6) inches are present.
- (3) A description of final grading and erosion controls.
(4) A time schedule indicating:
- (A) a time schedule for completion of each activity.
- (B) the estimated date of final completion of the closure activity.
- (f) Examples. Refer to Appendix O, "Examples of Lagoon Installation" for examples.
Added at 16 Ok Reg 1895, eff 6-11-99
Amended at 18 Ok Reg 1616, eff 6-1-01
Amended at 21 Ok Reg 1618, eff 6-11-04
Amended at 25 Ok Reg 2318, eff 7-11-08
Amended at 37 Ok Reg 1296, eff 9-15-20