The permit application is a six-step process:
- (1) Submit a feasibility study;
- (2) Submit a pilot study protocol, if required;
(3) Submit a Wasteload Allocation (Modification) Request letter:
- (A) The applicant shall be required to provide a hydrodynamic water quality model and a hydrologic mass balance model; and
- (B) Any new or modified wasteload allocations require an update to the Oklahoma Water Quality Management Plan (208 Plan) which also requires approval from EPA Region 6.
- (4) Submit an engineering report (as described in OAC 252:656-3-4), including the results from pilot studies. Also, the engineering report shall be accompanied by the proposed Parameter Monitoring Lists as described in OAC 252:628-11-7;
- (5) Submit an OPDES permit application (as described in OAC 252:606) along with the Contingency Plan described in OAC 252:628-1-3(h); and
- (6) Submit the final design report (as described in OAC 252:656-3-5) along with the required application forms.
Added at 35 Ok Reg 1311, eff 9-15-18