- (a) Backwash water. Provide adequate backwash water storage tanks, pump units, or finished water storage, to adequately backwash filters.
(b) Clearwell. In addition to the requirements of OAC 252:626-17-1 (a) - (c) and (f) - (r), the following requirements shall apply to clearwells:
- (1) Construct the top of the clearwell at least 5 feet above the 100-year flood plain.
- (2) Size clear wells to provide adequate reserves of treated water for filter washing, pumping to distribution, and for emergencies.
- (3) Do not locate the clear well under any part of a building where contamination is probable.
- (4) Do not allow a common wall with any basin holding untreated water.
- (5) Construct clearwells to prevent external leakage or seepage.
- (c) Basins and wet-wells. Design receiving basins and pump wet-wells for finished water as finished water storage structures.
Added at 18 Ok Reg 1612, eff 6-1-01