(a) Extension. The DEQ may extend the post-closure monitoring and care period if:
- (1) sampling shows the presence of elevated levels of any constituent;
- (2) evidence of contamination resulting from site operations is found to exist;
- (3) prior maintenance or monitoring of the site is found to be inadequate;
- (4) the site is producing leachate that must be treated prior to discharge; or
- (5) if other conditions are present that indicate a need for additional post-closure monitoring and care.
- (b) Additional requirements. When the post-closure period is extended, the DEQ may require the maintenance of existing financial assurance, the posting of additional assurance, and/or may require corrective action.
Added at 20 Ok Reg 1151, eff 6-1-03