(a) Explosive gas levels exceeded. During routine explosive gas monitoring, if gas levels exceed the limits specified in OAC 252:515-15-2, the owner/operator shall:
- (1) immediately take all necessary steps to ensure protection of human health and notify the DEQ;
- (2) within seven days of detection, submit to the DEQ in writing, the methane gas levels detected and a description of the steps taken to protect human health;
- (3) within 30 days of detection, submit a remediation plan to the DEQ for approval, describing the nature and extent of the problem and the proposed remedy; and
(4) within 60 days of detection, implement the remediation plan.
- (A) The plan may be modified to meet current conditions, with the written approval of the DEQ.
- (B) The DEQ shall be notified in writing when the remediation plan has been implemented and a copy placed in the operating record.
- (b) Alternative schedule. The DEQ may establish alternative schedules for demonstrating compliance with this Section.
Added at 20 Ok Reg 1151, eff 6-1-03