Okla. Admin. Code § 165:35-38-5
Self-build or Purchase Options
Effective Oct 1, 202441 Ok Reg, Number 23Added at 23 Ok Reg 699, eff 2-17-06 (emergency); Added at 23 Ok Reg 1666, eff 7-1-06; Amended at 27 Ok Reg 2098, eff 7-11-10; Amended at 36 Ok Reg 620, eff 7-25-19; Amended at 41 Ok Reg, Number 23, effective 10-1-24Corporation Commission
- (a) An electric utility may elect to file an application pursuant to 17 O.S. Section 286(C), as amended, and this subchapter seeking approval by the Commission to construct a new electric generating facility, to purchase an existing electric generation facility or to enter into a long-term contract for purchased power and/or energy.
- (b) Upon application by an electric utility pursuant to this Subchapter, the Commission shall review the requested cost recovery.
- (c) If the soliciting utility wishes to consider an option for full or partial ownership of a self-build option, the utility must submit its construction proposal ("Self-build Proposal") to provide all or part of the capacity requested in the RFP stated in 165:35-34 at the same time the bids are requested.
- (d) Once submitted, the Self-build Proposal may not be modified by the soliciting utility. If a Self-build Proposal is selected and approved by the Commission, the amount the soliciting utility shall recover through the rate base or other cost-recovery methods without additional Commission approval is limited to the total project cost identified in the Self-build Proposal.
- (e) A case shall be opened by the utility for cost recovery if the competitive bidding RFP process established in 165:35-34 is not utilized and the utility wishes to gain approval of cost before construction starts.
- (f) Bid responses will be opened with the Independent Evaluator, Commission and the Attorney General present.
- (g) Bid award terms and conditions shall be posted on the utility's web site or electronic bulletin board within sixty (60) calendar days after receipt, with a notice to the Commission.
(h) The Commission decision approving or denying the plan shall address the contents of the utility's resource plan, including its fuel procurement plan, purchased-power procurement plan, and risk management plan. If the record contains sufficient evidence, the Commission shall specifically approve or reject:
- (1) The utility's proposed plans for resources in the planning period,
- (2) The utility's proposed plans for acquiring additional resources through the competitive acquisition process, and
- (3) The utility's proposed RFP(s).
- (i) Upon the filing of an application pursuant to this Subchapter, the Commission will establish a procedural schedule, which shall provide for a Commission order within two hundred forty (240) calendar days of the date of such filing.
Added at 23 Ok Reg 699, eff 2-17-06 (emergency)
Added at 23 Ok Reg 1666, eff 7-1-06
Amended at 27 Ok Reg 2098, eff 7-11-10
Amended at 36 Ok Reg 620, eff 7-25-19
Amended at 41 Ok Reg, Number 23, effective 10-1-24