(a) On or before March 1 of each year, each charging station operator operating a public charging station shall electronically submit information required by the PUD, which includes but is not limited to the following:
- (1) Certification that the information provided under OAC 165:14-3-3(a) and (b) is accurate.
- (2) The number of EVSE ports located at each public charging station, sorted by physical address.
- (3) The name, telephone number, and electronic mail address of at least one person designated by the charging station operator to address questions pertaining to the report.
- (4) A certification stating that all testing has been completed pursuant to the requirements in this Chapter.
- (5) Applicable aggregate operational and transactional data for consideration in calculating the PBE as referenced in OAC 165:14-2-1.
- (b) One report may be submitted for multiple public charging stations if the information, other than the physical address and the number of EVSE ports, is the same.
- (c) No confidential information should be included in the report.
Added at 39 Ok Reg 950, eff 10-1-22
Amended at 41 Ok Reg, Number 23, effective 9-1-24