(A) For the purposes of this section and sections 4906.21 to 4906.232 of the Revised Code:
- (1) "Applicant" means an applicant for a certificate, or a material amendment to an existing certificate, from the power siting board to construct, operate, or maintain a utility facility, and includes any subsequent person to whom the certificate is transferred.
- (2) "Material amendment" and "utility facility" have the same meanings as in section 303.57 of the Revised Code.
- (B) At least sixty days prior to the commencement of construction of a utility facility, the applicant shall submit a comprehensive decommissioning plan for review and approval by the power siting board.