Ohio Rev. Code Ann. § 4113.61
(A)
(1) If a subcontractor or material supplier submits an application or request for payment or an invoice for materials to a contractor in sufficient time to allow the contractor to include the application, request, or invoice in the contractor's own pay request submitted to an owner, the contractor, within ten calendar days after receipt of payment from the owner for improvements to property, shall pay to the:
(2) If a lower tier subcontractor or lower tier material supplier submits an application or request for payment or an invoice for materials to a subcontractor, material supplier, or other lower tier subcontractor or lower tier material supplier in sufficient time to allow the subcontractor, material supplier, or other lower tier subcontractor or lower tier material supplier to include the application, request, or invoice in the subcontractor's, material supplier's, or other lower tier subcontractor's or lower tier material supplier's own pay request submitted to a contractor, other subcontractor, material supplier, lower tier subcontractor, or lower tier material supplier, the subcontractor, material supplier, or other lower tier subcontractor or lower tier material supplier, within ten calendar days after receipt of payment from the contractor, other subcontractor, material supplier, lower tier subcontractor, or lower tier material supplier for improvements to property, shall pay to the:
(B)
(2) In making a determination to award attorney fees under division (B)(1) of this section, the court shall consider all relevant factors, including but not limited to the following:
(D)
(E) Notwithstanding the definition of lower tier material supplier in this section, a person is not a lower tier material supplier unless the materials supplied by the person are:
(F) As used in this section: