(A) Not later than ninety days after the public meeting described in section 303.61 of the Revised Code regarding an application for a certificate, or a material amendment to an existing certificate, for a utility facility, the board of county commissioners may adopt a resolution that does either of the following:
- (1) Prohibits the construction of the utility facility that is the subject of the certificate;
- (2) Limits the boundaries of the proposed utility facility to a smaller geographic area of the county, completely within what was proposed by the applicant.
- (B) If no resolution is adopted within the time required under this section, the application may proceed as filed with the power siting board.
- (C) No resolution adopted under this section shall prevent an applicant from filing another proposal for consideration by the board of county commissioners at a later date.
Last updated July 23, 2021 at 4:44 PM