(a) The following requirements apply to leachate collection pipes:
(4) Leachate conveyance lines, gas condensate lines and appurtenances including manholes, sumps, and metering pits located outside the landfill liner system are not required to maintain the minimum separation of 5 feet from the seasonal high groundwater table, and are not required to maintain the minimum separation of 10 feet from bedrock.
(b) Materials required.
The leachate collection pipes must:
(3) be chemically compatible with leachate.
(c) Construction requirements.
Leachate collection pipes must be installed in accordance with the requirements of the approved engineering drawings, reports, and specifications and must be designed to have a minimum slope of one percent.
(d) Certification requirements.
The project engineer must certify that the requirements of paragraphs 363-6.6(a)(3) and (4) of this Subpart are met and that all leachate collection pipes are cleaned, debeaded and inspected upon completion of construction using video inspection equipment or other methods acceptable to the department to verify that the system is free of obstructions and construction-related debris.