N.Y. Comp. Codes R. & Regs. tit. 6, § 246.8
(a) the owner or operator of a MRP unit shall be exempt from the initial certification requirements of this section for a monitoring system under section 246.7(a)(1) if the following conditions are met:
(c) Except as provided in subdivision (a) of this section, the owner or operator of a MRP unit shall comply with the following initial certification and recertification procedures for a continuous monitoring system (i.e., a continuous emission monitoring system and sorbent trap monitoring system under 40 CFR 75.15). The owner or operator of a unit that qualifies to use the Hg low mass emissions excepted monitoring methodology under 40 CFR 75.81(b) or that also qualifies to use an alternative monitoring system under 40 CFR 75 subpart E shall comply with the procedures in subdivision (d) or (e) of this section respectively.
(2) Requirements for recertification.
(3) Approval process for initial certification and recertification. Subparagraphs (i) through (iv) of this paragraph apply to both initial certification and recertification of a continuous monitoring system under section 246.7(a)(1). For recertification, replace the words "certification" and "initial certification" with the word "recertification", replace the word "certified" with the word "recertified", and follow the procedures in 40 CFR 75.20(b)(5) in lieu of the procedures in subparagraph (v) of this paragraph.
(iv) Certification application approval process. The department will issue a written notice of approval or disapproval of the certification application to the owner or operator within 120 days of receipt of the complete certification application under subparagraph (ii) of this paragraph. In the event the department does not issue such a notice within such 120-day period, each monitoring system that meets the applicable performance requirements of 40 CFR part 75 and is included in the certification application will be deemed certified for use under the Mercury Reduction Program.
(v) Procedures for loss of certification. If the department issues a notice of disapproval of a certification application under clause (iv)(c) of this paragraph or a notice of disapproval of certification status under clause (iv)(d) of this paragraph, the following provisions apply:
(a) The owner or operator shall substitute the following values, for each disapproved monitoring system, for each hour of unit operation during the period of invalid data specified under 40 CFR 75.20(a)(4)(iii) or 75.21(e) and continuing until the applicable date and hour specified under of 40 CFR 75.20(a)(5)(i):