N.Y. Comp. Codes R. & Regs. tit. 6, § 246.3
(3) a new MRP unit shall be subject to the requirements of section 246.6 of this Part upon commencing operation.
(b) Emission testing.
(1) Any owner or operator of a MRP facility shall perform an emission test using a reference method for speciated mercury compounds and meet the requirements in subparagraphs (i), (ii), (iii) and (iv) of this paragraph:
(iii) Emission tests shall be conducted as follows:
(iv) Fuel sampling. During each emission test, sampling of the mercury and chlorine content of the coal or solid coal-derived fuel shall be performed as outlined in the approved test protocol and the results of the fuel sampling shall be included in the final report submitted to the department.
(c) Monitoring, reporting, and recordkeeping requirements.
(2) Unless otherwise provided, an owner or operator of the MRP facility shall keep on site at the facility each of the following documents for a period of five years from the date the document is created. This period may be extended by the department for cause, at any time before the end of five years, upon written notification.
(a) Mercury Reduction Program (MRP) requirements.