N.Y. Comp. Codes R. & Regs. tit. 6, § 246.11
(1) Report the Hg mass emissions data and heat input data for the MRP unit, in an electronic quarterly report in a format prescribed by the department and the administrator, for each calendar quarter beginning with:
(3) For MRP units that are also subject to an acid rain emissions limitation or the CAIR NOx Annual Trading Program, Clean Air Interstate Rule (CAIR) SO2 Trading Program, or CAIR NOx Ozone Season Trading Program, quarterly reports shall include the applicable data and information required by 40 CFR 75 subparts F through H as applicable, in addition to the Hg mass emission data, heat input data, and other information required by sections 246.7 through 246.13 of this Part.
(e) Compliance certification.
The owners or operators of a MRP facility shall submit to the department and the administrator, a compliance certification in support of each quarterly report based on reasonable inquiry of those persons with primary responsibility for ensuring that all of the unit's emissions are correctly and fully monitored. The certification shall state that:
(2) data are substituted in accordance with 40 CFR 75.34(a)(1) for all hours where Hg data are substituted for a unit with add-on Hg emission controls (a flue gas desulfurization system, a selective catalytic reduction system, or a compact hybrid particulate collector system).
(i)
(a) Recordkeeping provisions.
Owners and operators of a MRP facility shall comply with all recordkeeping requirements in this section and the applicable recordkeeping requirements of 40 CFR 75.84(a) through (c).
(b) Reporting provisions.
Owners and operators of a MRP facility shall comply with all reporting requirements in this section and the applicable reporting requirements of 40 CFR 75.84(d) through (f).
(c) Certification applications.
The owner or operator of a MRP facility shall submit an application to the department within 45 days after completing all initial certification or recertification tests required under section 246.9 of this Part, including the information required under 40 CFR 75.63.
(d) Quarterly reports.
Owners or operators of a MRP facility shall submit quarterly reports, as follows: