N.Y. Comp. Codes R. & Regs. tit. 6, § 242-1.4
(2) Any unit that, at any time on or after January 1, 2021, serves an electricity generator with a nameplate capacity equal to or greater than 15 MWe shall be a CO2 budget unit if either:
(ii) that unit resides at a source where there are two or more units with a nameplate capacity equal to or greater than 15 MWe. Any source that includes one or more such units shall be a CO2 budget source, subject to the requirements of this Part.
(b) Limited exemption for units, subject under paragraph (a)(1) of this section, with electrical output to the electric grid restricted by permit conditions.
(3) Compliance.
(v) On the earlier of the following dates, a unit exempt under paragraph (1) of this subdivision shall lose its exemption:
(vi) A unit that loses its exemption in accordance with subparagraph (v) of this paragraph shall be subject to the requirements of this Part. For the purpose of applying permitting requirements under Subpart 242-3 of this Part, allocating allowances under Subpart 242-5 of this Part, and applying monitoring requirements under Subpart 242-8 of this Part, the unit shall be treated as commencing operation on the date the unit loses its exemption.
(c) Limited exemption for units, subject under paragraph (a)(2) of this section, with electrical output to the electric grid restricted by permit conditions.
(1) Applicability. Notwithstanding paragraph (a)(2) of this section, any unit that meets the following conditions shall be exempt from the requirements of this Part, except for the provisions of this section and sections 242-1.2, 242-1.3, and 242-1.6 of this Subpart.
(3) Compliance.
(v) On the earlier of the following dates, a unit exempt under paragraph (1) of this subdivision shall lose its exemption:
(a) Units.