N.Y. Comp. Codes R. & Regs. tit. 6, § 236.4
(b) Once a leaking component is identified, any owner or operator subject to this Part must:
(d) The department may require the rescheduling of a planned process unit shutdown to an earlier date based on the number and severity of tagged leaks awaiting repair at shutdown. Before requiring a rescheduled shutdown, the department shall consider the effect of the shutdown on production, the availability of needed repair equipment, and the time required for contracting outside labor and/or rescheduling facility personnel and shall so direct the source owner in writing to comply with the rescheduled shutdown. The source owner shall comply with the department's directive, or shall request that a directed rescheduling of a planned process unit shutdown be reconsidered according to the following procedure: