N.Y. Comp. Codes R. & Regs. tit. 6, § 231-8.3
Prior to submitting a permit application, the facility owner or operator must comply with the requirements of section 231-12.3 (pre-application analysis for Subparts 231-7 and 231-8) of this Part.