N.Y. Comp. Codes R. & Regs. tit. 6, § 201-5.4
(a) The owner or operator of a facility subject to this Subpart must submit an application for permit modification, as described in section 201-5.2 of this Subpart, prior to commencing construction of either a significant modification as described in subdivision (b) of this section, or a minor modification as described in subdivision (c) of this section.
(1) The following changes to existing facilities are considered significant modifications:
(2) Applications for significant permit modifications are subject to the public noticing requirements for new applications pursuant to the requirements of Part 621 of this Title. The modified permit must be issued before the facility owner or operator may commence construction or operation of the requested modification.
(c) Minor permit modifications.
(3) The facility owner or operator may proceed with the requested minor modification upon receipt of a notice of complete application from the department confirming that the modification is minor. If the department fails to make a completeness determination, the application shall be deemed complete by default on the 15th day after receipt of the application and the facility owner or operator may proceed with the requested modification on the 25th day after the date that the department received the application. After the facility owner or operator makes the change and until the department takes final action, or notifies the facility owner or operator that the requested modification does not meet the minor modification criteria, the facility owner or operator must comply with both the applicable requirements governing the change and any proposed permit terms and conditions contained in the application. During this time period, the facility owner or operator need not comply with the existing permit terms and conditions for which a modification is proposed. However, if the facility owner or operator fails to comply with the proposed permit terms and conditions during this time period, the existing permit terms and conditions for which a modification is proposed may be enforced against it.
(d) Advance notifications.
The owner or operator of a facility subject to the requirements of this section may make changes that meet all of the criteria in paragraphs (1) through (4) of this subdivision without the prior approval of the department. The owner or operator of the facility must notify the department in writing at least 15 days in advance of making each such change, as described in subdivision (e) of this section.
(b) Significant permit modifications.
(e) Advance notifications required by subdivision (d) of this section shall include the following information: