N.Y. Comp. Codes R. & Regs. tit. 19, § 900-2.17
(a) A conceptual site plan, drawn at an appropriate scale, depicting all facility site driveway and roadway intersections, showing:
(b) A description of the pre-construction characteristics of the public roadways in the vicinity of the facility, as determined pursuant to the pre-application meeting(s) required pursuant to section 900-1.3(a) of this Part, including:
(c) An estimate of the trip generation characteristics of the facility during construction, including:
(d) An analysis and evaluation of the traffic and transportation impacts of the facility, including:
(f) If any construction or alteration is proposed that requires a notice of proposed construction to be submitted to the administrator of the FAA in accordance with 14 Code of Federal Regulations Part 77 (see section 900-15.1[h][1][i] of this Part):
(1) The application shall include a statement that the applicant has:
(2) If such construction or alteration of a wind facility is proposed to be located:
(iii) within three miles of the nearest point of the nearest point of the nearest landing and takeoff area of a commercial service, cargo service, reliever or general aviation (public use) heliport or military heliport:
(3) The application shall include a detailed description of the responses received in such reviews and consultations required in paragraphs (1) and (2) of this subdivision, including specifically whether and why such operators believe such construction or alteration should be:
Exhibit 16 shall contain: