N.Y. Comp. Codes R. & Regs. tit. 19, § 900-10.2
(a) Copies of all Federal and federally-delegated permits and approvals required for construction and operation of the facility.
(2) Letter(s) of credit (or other financial assurance approved by the ORES) and copies of agreements between the permittee and the towns, cities, and villages, establishing a right for each municipality to draw on the letters of credit dedicated to its portion of the facility shall be provided to the Office of Renewable Energy Siting after one year of facility operation and updated every fifth year thereafter specifying changes (due to inflation or other cost increases) to the structure of the letters of credit (or other financial assurance approved by the ORES).
(c) Plans, profiles, and detail drawings.
(3) Copies of any agreements entered with the owners/operators of existing high-pressure gas pipelines regarding the protection of those facilities.
(d) Wind turbine certifications.
(1) A design verification, confirming that the wind turbines were designed in accordance with international electrotechnical commission (IEC) 61400-1:2019 (see section 900-15.1[b][1][i] of this Part).
(e) Construction management.
(3) A facility maintenance and management plan, which shall include plans, procedures and criteria specifically addressing the following topics:
(4) A vegetation management plan, which shall include, at a minimum, the following:
(7) A complaint management plan, which shall describe, at a minimum, the following:
(iv) logging and tracking of all complaints received and resolutions achieved, with records of the following for each complaint containing:
(8) A traffic control plan shall be in effect during facility construction, to ensure safety and minimize potential delays to local traffic during construction, which shall describe, at a minimum, the following:
(iv) A copy of all road use and restoration agreements, if any, between the permittee and landowners, municipalities, or other entities, regarding repair of local roads damaged by heavy equipment, construction or maintenance activities during construction and operation of the facility.
(f) Environmental.
(4) A copy of the invasive species control and management plan (ISCMP), prepared in compliance with 6 NYCRR Part 575, which shall include the following information:
(5) a copy of an inadvertent return flow plan containing the following requirements:
(b) Final decommissioning.
(g) A copy of a cultural resources avoidance, minimization and mitigation plan, providing:
(2) A cultural resources mitigation and offset plan, either as adopted by Federal permitting agency in subsequent National Historic Preservation Act (NHPA) section 106 review, or as required by the office, in consultation with New York State Historic Preservation Office (SHPO) in the event that the NHPA section 106 review does not require that the mitigation plan be implemented. Proof of mitigation funding awards for offset facility implementation to be provided within two years of the start of construction of the facility shall be included.
(h) Real property rights.