N.Y. Comp. Codes R. & Regs. tit. 16, § 463.12
(c) The work order estimate shall include the following particulars:
(d) The work in progress record shall contain the following particulars:
(3) Full details at any time of the amount carried in account 103, construction work in progress, or account 144, Retirement Work in Progress, as applicable. The cost of completed projects shall be promptly transferred from those accounts to the accounts to which chargeable. Upon coming into service, completed portions involving additions to accounts shall be transferred to the appropriate account although other portions of the work covered by the same work order are not yet completed and the work order has not been closed. Credits for such transfers shall be made in separate column.
Note A:
Requirement of the use of the work order system here outlined may be suspended by order of the commission in the case of a utility which satisfies the commission that the system which it has in use for recording changes in steam plant accounts gives the equivalent detail by accounts in substantially the same form. The identification of expenditures with property must be complete and clear, and the detail of the cost of each project or job must be readily available. The total of the uncompleted projects must also be in agreement with account 103, Construction Work in Progress, or account 144, Retirement Work in Progress, as applicable.
Note B:
The work order system is required to record changes in steam plant used wholly or partly in steam operations. Its use is recommended, however, in recording other expenditures, such as for plant in other departments, repairs, etc. When used for repairs, balances applicable thereto shall be cleared monthly to the appropriate accounts.