(a) An application to construct a fuel gas transmission line which is less than 10 miles long, other than as described in section 85-1.2(a) of this Subpart, or section 120(2) of the Public Service Law, shall contain:
(1) the information required by:
(2) a description using text and detailed construction-type map (at a scale of 1 inch = 400 feet, or larger) showing the centerline and the specific relationship of the line to such features as:
(3) a statement explaining the need for the line, including:
(b) The applicant shall file and serve the application, in accordance with the requirements of section 3.5 of this Title and serve one copy each on:
(1) the central office and the appropriate regional offices of: