N.Y. Comp. Codes R. & Regs. tit. 14, § 813.6
(3) Upon receipt of an approved project proposal cost (proposed project approval, PPA) by the Division of Budget, project approval by applicant’s board of directors or authorized principal, approval of the State Attorney General and State Comptroller, an OASAS capital contract shall be executed including provisions for long term use of the facility and participation in the DASNY financing program for mental hygiene facilities.
(b) Application.
In addition to requirements for a State aid grant pursuant to section 813.5 of this Part, applicants for a DASNY loan shall provide the following:
(3) the applicant shall obtain a resolution of its board of directors authorizing the corporation to enter into such agreements as shall be required by DASNY and the office pursuant to Mental Hygiene Law and the Facilities Development Corporation Act.
(c) Recertification.
Applicants should initiate a certification process pursuant to Part 810 of this Title if the program is a new facility, is relocating to a new site, or is changing capacity consistent with the approved project plan.
(d) Accountability.
(4) The recipient of financial support must provide supervision and inspection at the construction site adequate to ensure that the work is completed on time and in accordance with office approved plans and specifications. Changes to approved plans or documents shall require the office's written approval.
(e) Allowable costs.
(2) Consistent with an approved capital contract or LOUI, a State aid grant or private financing to be refinanced with a DASNY loan may be used for the following costs:
(ix) such other costs as the commissioner may determine to be reasonable and necessary.
(f) Agreements.
(a) Eligibility.