N.Y. Comp. Codes R. & Regs. tit. 12, § 14-2.3
(b) The connections of such boiler when connected with other boilers that are under steam pressure shall be blanked off.
Exception:
Where double stop valves are installed in all connecting pipes with open drains between, such connections need not be blanked off.
The owner or user shall prepare a boiler for hydrostatic pressure test in the following manner: