Nev. Rev. Stat. § 338.530
1. If a public body receives:
(b) A contractor’s written notice of the correction of a condition set forth pursuant to subsection 2 of NRS 338.525 as the reason for the withholding, signed by an authorized agent of the contractor, and fails to:
(2) Object to the scope and manner of the correction, within 30 days after the public body receives the notice of correction, in a written statement that sets forth the reason for the objection and is signed by an authorized agent of the public body,
the public body shall pay to the contractor, in addition to the entire amount of the progress bill or retainage bill or any unpaid portion thereof, interest from the 30th day on the amount delayed, at a rate equal to the amount provided for in subsection 6 of NRS 338.515, until payment is made to the contractor.
(Added to NRS by 1999, 1985; A 2011, 1621; 2015, 2628)