Nev. Rev. Stat. § 338.485
2. A condition, stipulation or provision in a contract or other agreement that:
(c) Requires a contractor to waive, release or extinguish a claim or right for damages or an extension of time that the contractor may otherwise possess or acquire as a result of a delay that is:
(d) Requires a contractor or public body to be responsible for any consequential damages suffered or incurred by the other party that arise from or relate to a contract for a public work, including, without limitation, rental expenses or other damages resulting from a loss of use or availability of the public work, lost income, lost profit, lost financing or opportunity, business or reputation, and loss of management or employee availability, productivity, opportunity or services,
is against public policy and is void and unenforceable.
(Added to NRS by 1999, 1990; A 2011, 3703)