Nev. Rev. Stat. § 324.210
1. Upon the failure of any party having a contract with the State for the construction of irrigation works to begin the works within the time specified by the contract, or to complete the works within the time or in accordance with the specifications of the contract to the satisfaction of the State Engineer, the Division shall give the party written notice of the failure. If after a period of 60 days after the sending of the notice, the party fails to proceed with the work or to conform to the specifications of the contract, the bond and contract of the party and all works constructed under it are forfeited to the State. The Division shall at once so declare and give notice once a week for a period of 4 weeks in some newspaper of general circulation in the county or counties in which the work is situated, and in one newspaper at the State Capital in like manner and for a like period, of:
[15:76:1911; RL § 3078; NCL § 5489]—(NRS A 1975, 110; 1977, 1198; 1979, 233; 1991, 1765)