N.M. Stat. Ann. § 63-9I-5
A. This section applies to the activities of a wireless provider in installing a new, replacement or modified utility pole associated with the collocation of a small wireless facility in a right of way.
B. A new, replacement or modified utility pole associated with the collocation of a small wireless facility and installed in a right of way is not subject to zoning review and approval, except for that which pertains to the under-grounding prohibitions described in Subparagraph (c) of Paragraph (1) of Subsection C of this section, unless the utility pole, as measured from the ground level, is higher than whichever of the following is greater:
(1) ten feet plus the height in feet of the tallest existing utility pole, other than a utility pole supporting only one or more wireless facilities, that is:
(2) fifty feet.
C. An authority may require an application for the installation of a new, replacement or modified utility pole associated with the collocation of a small wireless facility in a right of way. An authority shall approve such an application unless the authority finds that the installation of the utility pole does not conform with:
(1) applicable codes or local laws concerning:
(5) the authority's laws concerning public safety and imposing minimum spacing requirements, if reasonable, for new utility poles in rights of way.
D. An authority shall process an application for a permit to install a new, replacement or modified utility pole associated with the collocation of a small wireless facility within one hundred fifty days after receiving the application. If the authority fails to approve or deny the application within that period, the authority shall deem the application approved. The application fee, if any, imposed by the authority for such an application shall conform with the requirements of Subsection M of Section 4 [63-9I-4 NMSA 1978] of the Wireless Consumer Advanced Infrastructure Investment Act and shall not exceed seven hundred fifty dollars ($750).
E. The installation, modification or replacement for which a permit is issued under this section shall begin within one hundred eighty days after the permit issuance date, unless the authority and wireless provider agree to extend that period or a delay in the installation, modification or replacement is caused by the lack of commercial power or fiber at the site. The permit gives the wireless provider the right to:
(2) subject to applicable relocation requirements, to the requirements imposed on the authority by this section and to the provider's right to terminate the installation at any time:
History: Laws 2018, ch. 17, § 5 and Laws 2018, ch. 69, § 5.