N.M. Code R. § 20.2.41.111
F. Test Notification, Reporting and Reevaluation of CEMS: The owner or operator of an existing or modified nonferrous smelter shall:
(1) Notify the Department at least forty-five (45) days in advance of the start of the field tests required at 40 CFR Part 52, Appendices D and E;
(2) Submit a report to the Department within forty-five (45) days of the completion of any performance specification test required by this Part or the Department; and
(3) Reevaluate the continuous emission monitoring systems installed and operated pursuant to subsection E of 20.2.41.111 NMAC at least once during any twelve (12) calendar months following the installation of such systems. The evaluation shall demonstrate acceptability of zero and calibration drift, relative accuracy error, and calibration error of measurements contained in the applicable performance specification at 40 CFR Part 52, Appendices D and E, or as otherwise approved by the Department.
[11/30/95; 20.2.41.111 NMAC - Rn, 20 NMAC 2.41.111 10/31/02]