N.M. Code R. § 19.8.28.2800
PERFORMANCE STANDARDS:
B. In situ processing activities shall be planned and conducted to minimize disturbance to the prevailing hydrologic balance by:
(1) avoiding discharge of fluids into holes or wells, other than as approved by the director;
(2) injecting process recovery fluids only into geologic zones or intervals approved as production zones by the director;
(3) avoiding annual injection between the wall of the drill hole and the casing; and
(4) preventing discharge of process fluid into surface waters.
D. Each person who conducts in situ processing activities shall prevent flow of the process recovery fluid:
(1) horizontally beyond the affected area identified in the permit; and
(2) vertically into overlying or underlying aquifers.
E. Each person who conducts in situ processing activities shall restore the quality of affected ground water in the permit and adjacent area, including ground water above and below the production zone, to the approximate premining levels or better, to ensure that the potential for use of the ground water is not diminished.
[11-29-97; 19.8.28.2800 NMAC - Rn, 19NMAC 8.2.28.2800, 9-29-2000]