N.M. Code R. § 19.8.14.1404
A. The amount of the bond required for each bonded area shall:
(1) be determined by the director;
(2) depend upon the requirements of the approved permit and reclamation plan;
(3) reflect the probable difficulty of reclamation, giving consideration to such factors as topography, geology, hydrology, and revegetation potential; and
(4) be based on, but not limited to, the estimated cost submitted by the permit applicant.
C. An operator's financial responsibility under 19.8.20.2069 and 2070 NMAC for repairing material damage resulting from subsidence may be satisfied by the liability insurance policy required under 19.8.14.1415 NMAC.
[11-29-97; 19.8.14.1404 NMAC - Rn, 19 NMAC 8.2.14.1404, 9-29-2000]