N.M. Code R. § 19.8.11.1108
EXISTING STRUCTURES:
B. If the director finds that the structure does not meet the requirements of Subsection A of 19.8.11.1108 NMAC, the director shall require the applicant to submit a compliance plan for modification or reconstruction of the structure and shall find prior to the issuance of the permit that:
(1) the modification or reconstruction of the structure will bring the structure into compliance with the design and performance standards of 19.8.19 through 19.8.28 NMAC as soon as possible, but not later than six months after issuance of the permit;
(2) the risk of harm to the environment or to public health or safety is not significant during the period of modification or reconstruction; and
(3) the applicant will monitor the structure to determine compliance with the performance standards of 19.8.19 through 19.8.28 NMAC.
C. Should the director find that the existing structure cannot be reconstructed without causing significant harm to the environment or public health or safety consistent with 19.8.20.2079 NMAC, the applicant will be required to abandon the existing structure. The structure shall not be used for or to facilitate surface coal mining operations after the effective date of issuance of the permanent regulatory program permit. Abandonment of the structure shall proceed on a schedule approved by the director.
[11-29-97; 19.8.11.1108 NMAC - Rn, 19 NMAC 8.2.11.1108, 9-29-2000; A, 4-28-2006; A, 12-31-2007]