N.M. Code R. § 19.10.11.1101
A. The Director shall conduct on-site inspections on an irregular basis according to the following schedule:
(1) at least two per year at each active existing and new mining operation;
(2) at least one per year at each inactive existing and new mining operation;
(3) at least one per year following completion of all significant reclamation activities, but prior to release of financial assurance; and
(4) at least one within the initial permit year and subsequently as determined by the Director for each minimal impact mining operation and for each exploration operation.
E. The Director or his authorized representative, without advance notice, shall:
(1) have the right of entry to, upon or through any mineral exploration, mining operation, or reclamation operation at any time to determine if the permittee is in compliance with the permit requirements and conditions; and
(2) at reasonable times, and without delay, have access to and copies of any records associated with permitting and compliance required by the Act, 19.10 NMAC, or the permit.
[7-12-94, 2-15-96, 7-31-97; 19.10.11.1101 NMAC – Rn, 19 NMAC 10.2.11.1101, 05-15-2001]